 12th Street Extension     
                                  
 
2007 Sanitary Sewer Slip Lining Program

 14th Avenue (G.R.I.P.) Sidewalk                

 7th Street
Resurfacing 34-41stAve

 2007 Alley Surfacing Program  

 
2007 Street Surfacing Program

 1st Street Water Main Replacement


12th Street Extension                                                                                                       Return to Top of Page

Project Description:   This project consists of the construction of new concrete street between 13th Avenue and Beacon Harbor Parkway near "The Quarter" Riverfront Development.  This project is driven by the potential for economic development along the south side of the new street as well as in The Quarter.

Schedule:                      March-June 2007 

Construction Cost:        $450,000 (Estimated)

Funding Source:            Motor Fuel Tax Funds

 2007 Sanitary Sewer Slip Lining Program                                            Return to Top of Page

Project Description:      This project combines repair of deteriorated sanitary sewers in East Moline, Moline, Rock Island and Coal Valley.  The combination of small projects to provide a large project for bidding and reduce the cost of construction by economy of scale.

Schedule:                      Construction in August-November 2007

Construction Cost:        $150,000 (Estimated)

Funding Source:            Sewer Capital Improvement Funds 

14th Avenue (G.R.I.P.) Sidewalk                                                                    Return to Top of Page

Project Description:      This project consists of the construction of new concrete sidewalk along the south side of 14th Avenue in front of the new Metrolink Transit Center located in the Great River Industrial Park (G.R.I.P.)  this sidewalk will provide pedestrian access between 10th Street and 13th Street as well as to the Metrolink facility and other local businesses.

Schedule:                      Construction in August 2007

Construction Cost:        $50,000 (Estimated)

Funding Source:            Motor Fuel Tax Funds

7th Street Resurfacing 34-41stAve                                                                Return to Top of Page

Project Description:      This project consists of milling and resurfacing 7th Street between 34th and 41st Avenues.  The existing street surface is rutted and  deteriorated due to high traffic volume.  The proposed improvements will provide a new wearing surface for the street.

Schedule:                      Construction in September-October 2007

Construction Cost:        $200,000 (Estimated)

Funding Source:            Motor Fuel Tax Funds

2007 Alley Surfacing Program                                                                           Return to Top of Page

Project Description:      This project consists of milling and resurfacing many badly deteriorated downtown alleys.  Please see the 2007 CIP map for specific blocks that are included in this program.

Schedule:                      Construction in September-November 2007

Construction Cost:        $550,000 (Estimated)

Funding Source:            80% Motor Fuel Tax Funds 20% Non-Home Rule Sales Tax Funds

2007 Street Surfacing Program                                                                           Return to Top of Page

Project Description:      This project consists of low-cost street surface improvements in the form of seal-coating, microsurfacing, and cape-sealing treatments to existing residential streets. A variety of street types are included with this program in which the City will test new street surfacing techniques in a variety of applications.  The results of this program will be utilized to assist in planning East Moline's 5-year Capital Improvement Plan for street maintenance and upgrades throughout the City. Please see the 2007 CIP map for specific blocks that are included in this year's program.

Seal-coating:     oil & chip surface

Microsurfacing: thin layer of polymer asphalt surface

Cape-Seal: seal-coat + microsurfacing

Schedule:                      Construction in September 2007

Construction Cost:        $225,000 (Estimated)

Funding Source:            Non-Home Rule Sales Tax Funds

2007 Ravine Storm Sewer Replacement Program                                          Return to Top of Page

Project Description:      This project consists of storm sewer replacement/repair and re-grading badly eroded portions of city storm sewers in areas where the storm pipes empty into ravines.  The program this year focuses on three (3) storm sewers in the ravine east of 5th Street.

Schedule:                      Construction in September-October 2007

Construction Cost:        $60,000 (Estimated)

Funding Source:            Drainage Capital Improvement Fund

 1st Street Water Main Replacement                                                                       Return to Top of Page

 Project Description:      This project consists of the replacement of a badly deteriorated water main along 1st Street from 16th Avenue to the dead-end south of the East Moline VFW Hall.  The proposed improvements will dramatically improve fire flow and water quality in the project area.  A $100,000 grant was received from Representative Mike Boland to assist the City with this project.

Schedule:                      Construction in September 2007 – May 2008

Construction Cost:        $300,000 (Estimated)

Funding Source:            $100k Grant, Water Capital Improvement Funds

 

 RETURN TO MAIN ENGINEERING PAGE 

 

 

 

 

 

 

 

 

 

 

 

 